Brent Harris — Work has continued throughout the warm Indiana weather over the past few days. The crew from FieldTurf have nearly completed the installation of the DuraSpine Pro surface at the soccer stadium and have the surface ready for play. Crews have added the new seats and will complete the final stages of the stadium over the next few weeks.

View the latest photos from the Mud Hollow project here.

Most of the attention will now turn to the practice fields and track and field competition areas on the eastern portion of Mud Hollow Field. Landscapers were laying the first sections of sod on Wednesday, and plan to have a entire green field in place by the weekend. With the new sod in place, crews were working on the irrigation system to make certain there will be no problems keeping the fields watered as the new grass takes root.

Fencing will be added in the coming weeks, along with some final pathways and landscaping, getting everything buttoned up for the debut and dedication of the new facilities in late August.